Demolition Environmental Enabling Civil Engineering Plant Hire

Kodak Factory - Harrow

- 30/10/20

Overview

Client: Barratt West London

Value: £9,000,000

Programme: 18 months

Overall recycle percentage: 92%

Scope of works: Demolition, hazardous waste removal, remediation and enabling works, groundworks and civil engineering

Description

The existing decommissioned Kodak factory was demolished in its entirety for redevelopment. Major asbestos removal to all the buildings was carried out by the Rye Group followed by the major demolition and site clearance of all the remaining buildings. The Rye Group also reprocessed the arisings and, following a reduced dig and remediation exercise, the site was stabilised and prepared for re-construction. All contaminated soils were remediated on site and prepared for re-use. The cart away from site was minimised to achieve the carbon footprint targets. All elements of the demolition arisings were recycled and processed for re-use.

Memberships And Accreditation Partners

BSC Logo
ISO 14001
ISO 45001
ISO 9001
NFDC
NDTG
SMAS
Build UK
FORS Silver
Construction Line Gold
Acclaim
CHAS Premium Plus
Considerate Contractors
CQMS